    How to Calculate Your Metal Fabrication Shop Rate

    A working shop rate is the hourly number you charge to break even on labor and overhead — and still leave room for profit. Get it wrong and every quote bleeds margin. Here is the model most metal fabrication shops use, and how MetalHub HQ keeps that rate applied consistently across every estimate.

    What a "shop rate" actually covers

    A shop rate is the per-hour cost of running one productive station — operator, machine, building, and a target profit margin all rolled into a single number that estimators can multiply against shop hours.

    It is not the same as the operator's wage. A wage ignores benefits, payroll taxes, machine depreciation, rent, utilities, insurance, and the profit you actually want to take home. Use raw wage and you will quote below cost.

    The three components

    1. Burdened labor. Operator wage plus payroll taxes, workers' comp, health insurance, paid time off, and training. A typical burden is 25–40% above base wage. A $28/hr welder usually costs $36–$39/hr fully loaded.
    2. Machine and shop overhead. Equipment depreciation, consumables, power, rent, property tax, insurance, software, and non-billable supervision — divided by the realistic billable hours per year (not 2,080; closer to 1,500–1,700 after PTO, setup, and idle time).
    3. Profit margin. What is left after labor and overhead. Most metal shops target 15–25% net on shop hours. Add it on top of cost; do not bury it inside an inflated wage figure.

    A worked example

    For a press-brake operator earning $28/hr, in a shop running a single brake:

    • Burdened labor: $28 × 1.30 = $36.40/hr
    • Machine + shop overhead allocated to the brake station: $58,000/yr ÷ 1,600 billable hours = $36.25/hr
    • Cost subtotal: $72.65/hr
    • Target 20% profit: $72.65 ÷ (1 - 0.20) = $90.81/hr shop rate

    Round to a clean number ($90 or $95) and use it as the brake's standard shop rate. Repeat per station — laser, shear, weld, finish — because each station's overhead and utilization differ.

    Why most shop rates drift

    • Estimators apply the rate inconsistently — one quote at $85, the next at $95.
    • Catalog prices were set last year and never re-derived from the shop rate.
    • Material adders (coil vs. sheet, finish upcharges) get forgotten on rushed quotes.
    • No audit trail when a customer disputes the labor line two months later.

    How MetalHub HQ keeps the rate consistent

    Inside MetalHub HQ the shop rate lives in your vendor pricing catalog, not in an estimator's head. Every line item — labor, machine time, finish — pulls from the same catalog, so the rate you computed above is the rate every quote uses.

    • Pricing catalog stores per-station unit prices (LF, piece, sqft, hour).
    • Material Cutting Calculator applies coil vs. sheet adders automatically.
    • Every quote and revision is versioned, so the rate at quote-time is auditable.
    • Bulk catalog updates re-price open drafts when you raise the shop rate.